PROJECT SUMMARY Harrods Central Escalators, Knightsbridge

41 TOWER HILL 41 TOWER HILL41 TOWER HILL

Central Escalator Installation

Client:Harrods Ltd
Constructor:Norwest Holst
Project Value: £21M
Completion:2008
Our Services:Quantity Surveying
Client Type:Retail
Contract Period:78 weeks
Contract:JCT Prime Cost
Work Environment:In occupation
Other Consultants:Project Managers - Harrods Ltd
 Architects: Lee Reading
 Harbinson
Structural Eng: Colin Toms & Partners Services Eng: Carl Bro Group

The contract comprised the removal of the existing passenger lifts, extensive structural alterations to facilitate the installation of new escalators forming the new circulation hub for the store. The works included extensive mechanical & electrical alterations & re-wiring. The finishes & fittings were installed by specialists & artisans incorporating extensive hand cut glass & bronze. All work had to be carried out without disruption to the sales floors which involved extensive out of hours working. Delivery of materials needed to be co-ordinated with store deliveries.